It will take more than half a year for Metro to recover fully from an electrical fire that knocked out service on much of the Blue, Orange, and Silver lines earlier this week, the transit authority said Friday. Trains on those lines will run 33 percent less frequently to reduce them from bunching up at the Stadium-Armory station, where Monday’s blaze took out a power substation.
Metro severely restricted Blue, Orange, and Silver service for more than nine hours in some places Monday after a nine-megawatt substation near Stadium-Amory caught fire. In the wake of the incident, Metro is keeping Stadium-Armory operational with power drawn from other substations throughout the train system. Because those substations were already functioning at capacity, though, Metro is throttling the juice it sends to Stadium-Armory, meaning only one train per track can pass through at a time.
The upshot is that Blue, Orange, and Silver trains have been lurching into Stadium-Armory with frequent halts. To alleviate that condition, Metro’s solution is to reduce the rush-hour frequency of the Orange and Silver lines from one train every six minutes to eight minutes, and the Blue Line to one train every 12 minutes.
In a press release, Metro says it will attempt to increase the number of eight-car trains on the Silver and Orange lines. But the diminished frequency of trains and the speeds at which they can run are expected to make crowding on the affected lines worse
Rob Troup, Metro’s deputy general manager, told the transit authority’s board Friday it could take at least six months for the Stadium-Armory substation to be fully operational again.
Benjamin Freed joined Washingtonian in August 2013 and covers politics, business, and media. He was previously the editor of DCist and has also written for Washington City Paper, the New York Times, the New Republic, Slate, and BuzzFeed. He lives in Adams Morgan.
Metro Says Blue, Orange, and Silver Lines Will Run Slowly for Months
It will take more than half a year for Metro to recover fully from an electrical fire that knocked out service on much of the Blue, Orange, and Silver lines earlier this week, the transit authority said Friday. Trains on those lines will run 33 percent less frequently to reduce them from bunching up at the Stadium-Armory station, where Monday’s blaze took out a power substation.
Metro severely restricted Blue, Orange, and Silver service for more than nine hours in some places Monday after a nine-megawatt substation near Stadium-Amory caught fire. In the wake of the incident, Metro is keeping Stadium-Armory operational with power drawn from other substations throughout the train system. Because those substations were already functioning at capacity, though, Metro is throttling the juice it sends to Stadium-Armory, meaning only one train per track can pass through at a time.
The upshot is that Blue, Orange, and Silver trains have been lurching into Stadium-Armory with frequent halts. To alleviate that condition, Metro’s solution is to reduce the rush-hour frequency of the Orange and Silver lines from one train every six minutes to eight minutes, and the Blue Line to one train every 12 minutes.
In a press release, Metro says it will attempt to increase the number of eight-car trains on the Silver and Orange lines. But the diminished frequency of trains and the speeds at which they can run are expected to make crowding on the affected lines worse
Rob Troup, Metro’s deputy general manager, told the transit authority’s board Friday it could take at least six months for the Stadium-Armory substation to be fully operational again.
Benjamin Freed joined Washingtonian in August 2013 and covers politics, business, and media. He was previously the editor of DCist and has also written for Washington City Paper, the New York Times, the New Republic, Slate, and BuzzFeed. He lives in Adams Morgan.
Most Popular in News & Politics
Rax King’s New Essay Collection Celebrates the “Sloppy” Side of DC Culture
Congressman Proposes Renaming Entire Kennedy Center for Trump, Poll Says Most Americans Are Paying Attention to Epstein Story, and We Tell You Where to Get a Mahjong Game
Inside the Library of Congress’s Collection
Trump Wants to Prosecute Beyoncé, That DC “Worst Traffic” Study Is Flawed, and Our Food Critic Tried Lucky Danger
Jonathan Swan’s Face Is the 2020 Meme We Needed
Washingtonian Magazine
August Issue: Best Burgers
View IssueSubscribe
Follow Us on Social
Follow Us on Social
Related
Need to Know What Time It Is? 6 Places to Find a Sundial Around DC.
Every Bus Line in DC Is Changing This Weekend. Here’s What to Know.
DC Sues More Maryland and DC Drivers
How Would a New DC Stadium Compare to the Last One?
More from News & Politics
Who Will Run for Eleanor Holmes Norton’s Seat? A Guide to the Candidates and Rumors.
Musk’s “America Party” Goes the Way of His DC-Baltimore Tunnel, More Big Names Leave the Post, and Biden Got Some Ice Cream in MoCo
Up All Night in DC, the City That Very Much Sleeps
Journalists Savor Prospect of Pete Hegseth Running for Office, Trump Wants a White House Ballroom, and Katie Ledecky Won Another World Title
Eric Adjepong on Mixing Tradition and Modernity at His DC Restaurant Elmina
Can the Education Department Really Force Virginia Schools to Change Their Policies About Trans Kids?
Rax King’s New Essay Collection Celebrates the “Sloppy” Side of DC Culture
Congressman Proposes Renaming Entire Kennedy Center for Trump, Poll Says Most Americans Are Paying Attention to Epstein Story, and We Tell You Where to Get a Mahjong Game