Surprise! The second phase of Metro’s Silver Line—better known as the part that will finally connect Dulles International Airport to the rest of the rail network—is being delayed by 13 months, the Metropolitan Washington Airports Authority says in a press release. As a result, access to Dulles will remain roads-only until late 2019 or even 2020 instead of the former target opening date in 2018.
The delay, which was first reported by NBC4’s Adam Tuss, is the result of more than 150 design modifications to Phase 2 of the Silver Line, which also includes several non-airport stops in Loudoun County. (In a separate decision, Metro last week settled on the names of its Loudoun County stations.)
Phase 1 of the Silver Line, running 11.7 miles between East Falls Church and Reston, famously suffered several delays. Construction began in March 2009, nearly four years later than planners initially aimed for. Its entry into service, initially targeted for the end of 2013, did not happen until last July. In its announcment today, MWAA also says Phase 1 needs another $76 million worth of finishing touches, adding 2.6 percent to its $2.9 billion cost, though the additional figure is still within its federally approved budget. Phase 2, which will run 11.5 miles from Reston to Ashburn, is expected to cost $2.7 billion.
Benjamin Freed joined Washingtonian in August 2013 and covers politics, business, and media. He was previously the editor of DCist and has also written for Washington City Paper, the New York Times, the New Republic, Slate, and BuzzFeed. He lives in Adams Morgan.
Silver Line to Dulles Delayed Until at Least 2019
You'll have to drive to the airport for a bit longer than originally expected.
Surprise! The second phase of Metro’s Silver Line—better known as the part that will finally connect Dulles International Airport to the rest of the rail network—is being delayed by 13 months, the Metropolitan Washington Airports Authority says in a press release. As a result, access to Dulles will remain roads-only until late 2019 or even 2020 instead of the former target opening date in 2018.
The delay, which was first reported by NBC4’s Adam Tuss, is the result of more than 150 design modifications to Phase 2 of the Silver Line, which also includes several non-airport stops in Loudoun County. (In a separate decision, Metro last week settled on the names of its Loudoun County stations.)
Phase 1 of the Silver Line, running 11.7 miles between East Falls Church and Reston, famously suffered several delays. Construction began in March 2009, nearly four years later than planners initially aimed for. Its entry into service, initially targeted for the end of 2013, did not happen until last July. In its announcment today, MWAA also says Phase 1 needs another $76 million worth of finishing touches, adding 2.6 percent to its $2.9 billion cost, though the additional figure is still within its federally approved budget. Phase 2, which will run 11.5 miles from Reston to Ashburn, is expected to cost $2.7 billion.
Benjamin Freed joined Washingtonian in August 2013 and covers politics, business, and media. He was previously the editor of DCist and has also written for Washington City Paper, the New York Times, the New Republic, Slate, and BuzzFeed. He lives in Adams Morgan.
Most Popular in News & Politics
Here Are Your Rights at an ICE Checkpoint in DC
Sandwich Guy Has Become DC’s Hero
Politics and Prose’s Self-Publishing Business Is Booming
PHOTOS: The Outrageous Style of the North American Irish Dance Championships
Meet the Lobbyist Fighting Against “Perfectly Legal” Corruption in DC
Washingtonian Magazine
September Issue: Style Setters
View IssueSubscribe
Follow Us on Social
Follow Us on Social
Related
The Confusing Dispute Over the Future of the Anacostia Playhouse
Protecting Our Drinking Water Keeps Him Up at Night
PHOTOS: The Outrageous Style of the North American Irish Dance Championships
This Quirky DC Map Isn’t Like Any You’ve Ever Seen
More from News & Politics
The Confusing Dispute Over the Future of the Anacostia Playhouse
JD Vance Booed Again, This Time in Union Station; DC Residents Overwhelmingly Oppose Trump’s Takeover; and Bob McDonnell Got a New Job at George Mason
Protecting Our Drinking Water Keeps Him Up at Night
Trump Thinks the Smithsonian Is Too Obsessed With Slavery, Jeanine Pirro Was Appalled by Sean Hannity’s Use of the Oval Office Bathroom, and It Just Got Easier to Carry a Shotgun in DC
PHOTOS: Protests Around DC of Trump’s Takeover
Low-Crime States Mississippi and Louisiana Send Troops to DC, Trump Incorrectly Claims He’s Helped DC Restaurants, and Key Bridge Was Closed Because of Ukraine Summit
PHOTOS: The Outrageous Style of the North American Irish Dance Championships
Sandwich Guy Has Become DC’s Hero